Wynyard Central

Client

Downer

Location

Wynyard Quarter

Tender Value

$5M

Commencement Date

Final Construction Value

$6.2M

Final Completion Date

October 2020

This project was a complete streetscape upgrade of Daldy St & Gaunt St in Wynyard Qtr. The job consisted of carriageway paving (concrete, basalt paving, & asphalt), footpath upgrade, rain garden construction, precast & in-situ concrete structures, street furniture install, boardwalk construction, & grassed play areas. As one of the final pieces of the Wynyard Qtr upgrade this project was much anticipated and the final result has been outstanding.

With the growth in business’s around Wynyard Qtr much of the project revolved around staging progress to maintain access to both commerical business’s and residential apartments without disruption/delay. This was succesully managed with stakeholder in put throughout the job.

Final surfaces of very high quality were delivered with constant monitoring and strict controls. The design called for many different finishes with small details such as uplights within the footpaths & boardwalks, Corten Steel edging & walkways, paving around tram tracks, and a paving design incorporating many different sizes and patterns.